Dallah delays Namar hospital launch; cost rises to SAR 920 mln

06/07/2015 Argaam

Dallah Healthcare Holding Co will postpone the operation of the first stage of its Namar hospital project in Riyadh to the third quarter of 2017, previously scheduled to open in 2016, as the company has expanded the project to increase the capacity of the hospital,

 

The second stage of the project will be ready by the third quarter of 2018, Dallah said in a statement to the Saudi exchange, Tadawul.

 

As a result of the expansion, the cost of the project has increased to SAR 920 million from SAR 508 million. Up to SAR 360 million will be financed from the company’s IPO proceeds, SAR 100 million from the firm’s operations, and the remaining cost will be funded through loans from local banks and the ministry of finance, it added.

 

In July 2014, the healthcare provider signed a sharia-compliant SAR 955.5 million loan with the Saudi British Bank (SABB) to finance the construction of new hospitals, including Namar. 

 

Namar Hospital – (Western Riyadh)

Comments {{getCommentCount()}}

Be the first to comment

loader Train
Sorry: the validity period has ended to comment on this news
Opinions expressed in the comments section do not reflect the views of Argaam. Abusive comments of any kind will be removed. Political or religious commentary will not be tolerated.