Jazan Development Co. announces the latest developments of its Building Complex as following:
1. The event in the previous announcement: The start of its Building Complex
2. Announced on 26-08-2008
3. Progress rate achieved is 92%
4. Expected Finishing of this event is on 30-06-2014
5. The delay reasons delay in getting approvals for services, utilities, shortage of skilled labor in the area and termination of some contracts and entering into new contracts with other contractors.
6. Cost related of event is increased due to increase in Building materials and labor cost.
7. Expected financial impact of delay on financial statement: No negative impact due to high increase in rent (expected income) in the area.
Argaam Investment Company has updated the Privacy Policy of its services and digital platforms. Know more about our Privacy Policy here.
Argaam uses cookies to personalize content, to provide social media features and analyze traffic, that we might also share with third parties. You consent to our cookies if you use this website
Comments {{getCommentCount()}}
Be the first to comment
رد{{comment.DisplayName}} على {{getCommenterName(comment.ParentThreadID)}}
{{comment.DisplayName}}
{{comment.ElapsedTime}}