Najran Cement Company expects the trial run for all phases of the Waste Heat Recovery project (WHR) to continue till June 2014.

According to data available by Argaam; the Cement maker started the trial run for phase1 of WHR project on January 11, 2014 and said it is to last till the end of April.

The 2 phases’ project has a production capacity of 12.2 megawatt per hour for phase1 and 27.1 megawatt per hour for phase2 which was expected to commence trial operations in March.