Tabuk Cement announces developments of new mill

26/05/2013 Argaam

Further to Tabuk Cement’s announcements on 25/5/2013 on the latest developments of the new mill project, the company would like to inform stakeholders that the project’s cost announced on 2/7/2011 remain unchanged.

 

The company also states that construction works of the project have taken around two and half months past the schedule announced earlier, due to a belated execution by the contractor.

 

The mill’s test operation is expected to take almost two months, and commercial operation will be announced in due course. 