King Abdullah Port completes 3,200 tons general cargo handling for Petro Rabigh project

30/03/2020 Argaam

 

Saudi Arabia’s King Abdullah Port announced in a statement today the successful completion of the last phase of handling 3,200 tons of machines for the Petro Rabigh Phase II upgrading.

 

Five international companies cooperated during the process of transporting the cargo from outside Saudi Arabia until its arrival in King Abdullah Port and then on to the Petro Rabigh project.

 

The unloading and handling processes were carried out in the bulk and general cargo terminal with King Abdullah Port’s latest technologies and cranes, which enable the port to handle huge volumes of cargo.

 

The industrial equipment included steamers, splitter condensers, heat pump desuperheaters, and debutanizer reboilers, the statement added.

Comments {{getCommentCount()}}

Be the first to comment

loader Train
Sorry: the validity period has ended to comment on this news
Opinions expressed in the comments section do not reflect the views of Argaam. Abusive comments of any kind will be removed. Political or religious commentary will not be tolerated.